Between downtown and Fresno’s Chinatown, progress continues on the Tulare Street underpass. Both tracks of the Union Pacific railroad have been cutover to the shoofly, a temporary track built for the construction of the grade separation. Also, the west approach retaining walls and excavation under G Street is now complete. Crews have also installed the falsework for the G Street Bridge, placed concrete to form the bridge deck, and are now preparing to begin post-tensioning the ducts inside the bridge deck.
CP 1: Tulare Street Underpass