Skip to Main Content

CP 4: Kimberlina Viaduct

Worker smoothing concrete at Kimberlina viaduct.

In March, crews completed the lower deck of the Kimberlina Viaduct by placing 560 cubic-yards of concrete in the span of seven hours. Crews will start working on the stem walls by continuing to tie rebar and placing concrete throughout the spring. When complete, the Kimberlina Viaduct will be 110-feet long and will take high-speed trains over traffic.