In August, crews began placing pre-cast concrete girders for the superstructure of the Hanford Viaduct. Each wide flange girder ranges in size between 53 to 74-feet long and weighs between 60,000 to 90,000 pounds. As many as 14 girders will be placed between each span of columns, and more than 900 girders will be needed all together. As of Oct. 1, 2022, more than 130 girders have been placed across 15 spans of columns.