Skip to Main Content

Avenue 12 Grade Separation

A little east of Madera Community College, crews have poured the concrete deck and are now setting concrete forms for barrier walls along the sides of the Avenue 12 overcrossing. Walls adjacent to the Avenue 12 overpass crossing the existing freight rail line are also being constructed. The recent rains slowed down the progress of the footings, but walls are starting to be formed on the west side of the tracks. The realignment of the busy roadway with two separate bridges will take traffic over the high-speed rail line and the BNSF freight tracks a little further east.