On the Avenue 11 bridge, crews are completing traffic barriers on the bridge. Next, dirt, paving, and guardrail crews will be mobilizing to complete the overpass, starting with the roadway leading up to the concrete bridge deck. A rock base will then be placed for the roadway followed by asphalt paving. This crossing, east of Road 30 ½, will take traffic over the high-speed train alignment.